13. Jun 2025. EIA, News

The consent for the Environmental Impact Assessment Study for the construction of the poultry farm complex on cadastral parcel No. 2809/13, Cadastral Municipality of Bačka Topola, has been obtained.

On Monday, April 28th, 2025, a public hearing was held at the premises of the Municipality of Bačka Topola, where employees of “Aurora Green” d.o.o. presented the Environmental Impact Assessment Study for the project involving the construction of a poultry farm complex with a capacity of 315,000 broilers per production cycle, i.e. 45,000 broilers per facility per cycle, located on cadastral parcel No. 2809/13, Cadastral Municipality of Bačka Topola. The presentation was followed by a discussion with the interested public in attendance.

For the subject project, the Technical Commission submitted a Report with a positive assessment of the Study, and the Competent Authority issued a Decision granting consent to the Environmental Impact Assessment Study on June 11th, 2025.